Drilling Update for Giant Welchau Gas Prospect
“Well site construction is complete, the drill rig is expected to
become available next week and commencement of drilling is
expected during the following week.”
Key points:
All regulatory requirements are in place to commence drilling operations at the Welchau
gas exploration project, in the ADX-AT-II licence in Upper Austria.
Well site construction at the Welchau-1 drill site is complete.
The RED Drilling & Services GmbH (RED) E202 drilling rig is expected to become
available to ADX at the end of next week (Rig Release).
The well will be spudded after mobilisation and rig assembly which will take approximately
7 days after Rig Release. The duration of drilling operations is approximately 39 days.
In accordance with an Energy Investment Agreement with MCF Energy Ltd., via its
subsidiary MCF Energy GmbH (MCF), MCF will fund 50% of the Welchau-1 well costs up
to a cap of EUR 5.1 million to earn a 25% economic interest in the Welchau Investment
Area. Upon completion of MCF’s funding obligations ADX will hold a 75% economic
interest in the Welchau Investment Area.
The Welchau gas prospect has exceptional gas resource potential, located in the heart of
Europe at a relatively shallow drill depth and proximal to gas pipelines. ADX estimates that
Welchau has best technical Prospective Resources of 807 BCFE (134 MMBOE) 1. Welchau
is targeting the same reservoirs as the nearby Molln-1 well which tested condensate rich,
pipeline quality gas at rate of 4.0 MMSCFPD in 1989.
Prospective Resources are those estimated quantities of petroleum that may potentially be
recovered by the application of a future development project(s) related to undiscovered
accumulations. These estimates have both an associated risk of discovery and a risk of
development. Further exploration appraisal and evaluation is required to determine the
existence of a significant quantity of potentially moveable hydrocarbons.
ADX Executive Chairman, Mr Ian Tchacos, said, “We are poised to commence operations
at Welchau. On behalf of the Board, I would like to thank our Austrian team for their diligence
in securing all the necessary regulatory approvals and achieving operational readiness to drill
this important gas well. Achieving regulatory approvals at Welchau has exceeded the usual
less than 6 month licensing process in Austria due to greater environmental sensitivities at the
Welchau location as result of its proximity to an area of touristic interest and a small nature
protection area. Despite these additional environmental and community considerations the
licensing process in Austria has been far more predictable and timely than other jurisdictions
such as many other parts of Europe, the U.K. and Australia where such approvals can take
up to two years”.
¹ Best Technical Prospective Resources Prospective resources reporting date 22.06.2023
ADX Energy Ltd | ABN 50 009 058 646 -Registered and Principal Office Australia
29 Bay Road, Claremont WA 6010, Australia
Telephone: +61 8 9381 4266 | admin@adxenergy.com.au | adxenergy.com.au
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
ADX Energy Ltd (ASX Code: ADX) is pleased to advise the imminent mobilisation of the RED E-202 drilling rig
to the Welchau-1 rig site within the ADX-AT-II licence in Upper Austria (see figure 1). Well site construction
commenced on the 15th of December 2023 following receipt of the environmental clearance and is now
complete. The success case drilling program is expected to take approximately 39 days.
Figure 1: Map showing ADX-AT-II license area and the Welchau-1 drilling location in the Northern Calcareous Alps
Figure 2: The completed well site at the Welchau-1 drilling location which is now available for drilling
ADX Energy Ltd | ABN 50 009 058 646 -Registered and Principal Office Australia
29 Bay Road, Claremont WA 6010, Australia
Telephone: +61 8 9381 4266 | admin@adxenergy.com.au | adxenergy.com.au
Page | 2
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
Operational Readiness
ADX has contracted the necessary services and purchased all the long lead items required to drill the Welchau1 well. The drilling of the well will be under an existing rig services contract with RED. The RED E202 drilling rig
is expected to become available to ADX at the end of next week following the scheduled completion of work
with another Operator in Upper Austria. The RED E202 drilling rig has been pre-approved for the Welchau-1
well based on the required safety, noise and environmental emission standards.
ADX used the RED E202 drilling rig to drill the Company’s first exploration well in Austria (Anshof-3) as well as
the Anshof-2 well. Both wells were drilled without any lost time safety incidents and within budget. The drilling
services and other contracted services will be almost exclusively provided by highly trained local staff from
Upper Austria, as was the case for the Anshof-2 and Anshof-3 wells. ADX has endeavoured to maximise local
content where there is an excellent past record of safety, environmental protection and project execution.
Economic Participation in the Welchau Investment Area
ADX has executed an Energy Investment Agreement with MCF Energy Ltd. via its subsidiary MCF Energy
GmbH (MCF) to fund 50% of Welchau-1 well costs up to a well cost cap of EUR 5.1 million to earn a 25%
economic interest in the Welchau Investment Area which is part of ADX’s ADX-AT-II licence in Upper Austria.
The Welchau Investment Area contains the Welchau Gas Prospect and other emerging oil and gas prospects.
Upon completion of MCF’s funding obligations ADX will hold a 75% economic interest in the Welchau Investment
Area. ADX holds a 100% economic interest in the remainder of the ADX-AT-II license other than the Anshof
Discovery Area.
For further details please contact:
Ian Tchacos
Executive Chairman
+61 (08) 9381 4266
ian.tchacos@adxenergy.com.au
Authorised for lodgement by Ian Tchacos, Executive Chairman
Persons compiling information about Hydrocarbons:
Pursuant to the requirements of the ASX Listing Rule 5.41 the technical and reserves information relating to
Austria and Italy contained in this release has been reviewed by Paul Fink as part of the due diligence process
on behalf of ADX. Mr Fink is Technical Director of ADX Energy Ltd is a qualified geophysicist with 30 years of
technical, commercial and management experience in exploration for, appraisal and development of oil and gas
resources. Mr Fink is a member of the EAGE (European Association of Geoscientists & Engineers) and FIDIC
(Federation of Consulting Engineers).
Previous Estimates of Reserves and Resources:
ADX confirms that it is not aware of any new information or data that may materially affect the information
included in the relevant market announcements for reserves or resources and that all material assumptions and
technical parameters underpinning the estimates in the relevant market announcements continue to apply and
have not materially changed.
ADX Energy Ltd | ABN 50 009 058 646 -Registered and Principal Office Australia
29 Bay Road, Claremont WA 6010, Australia
Telephone: +61 8 9381 4266 | admin@adxenergy.com.au | adxenergy.com.au
Page | 3
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
Reporting Standards for Resource Estimation
Reserves and resources are reported in accordance with the definitions of reserves, contingent resources and
prospective resources and guidelines set out in the Petroleum Resources Management System (PRMS) prepared
by the Oil and Gas Reserves Committee of the Society of Petroleum Engineers (SPE) and reviewed and jointly
sponsored by the American Association of Petroleum Geologists (AAPG), World Petroleum Council (WPC),
Society of Petroleum Evaluation Engineers (SPEE), Society of Exploration Geophysicists (SEG), Society of
Petrophysicists and Well Log Analysts (SPWLA) and European Association of Geoscientists and Engineers
(EAGE), revised June 2018.
Prospective Resource Classifications
Low Estimate scenario of Prospective Resources - denotes a conservative estimate of the quantity that will
actually recovered from an accumulation by an oil and gas project. When probabilistic methods are used, there
should be at least a 90% probability (P90) that the quantities actually recovered will equal or exceed the low
estimate.
Best Estimate scenario of Prospective Resources - denotes the best estimate of the quantity that will actually be
recovered from an accumulation by an oil and gas project. It is the most realistic assessment of recoverable
quantities if only a single result were reported. When probabilistic methods are used, there should be at least a
50% probability (P50) that the quantities actually recovered will equal or exceed the best estimate.
High Estimate scenario of Prospective Resources - denotes an optimistic scenario of the quantity that will
actually be recovered from an accumulation by an oil and gas project. When probabilistic methods are used, there
should be at least a 10% probability that the quantities actually recovered will be equal or exceed the high
estimate.
Nomenclature and conversions used in this release
BBL means US barrel
MMBBLS means millions of US barrels
MCF means thousand cubic feet
MMCF means million cubic feet
BCF means billion cubic feet
TCF means trillion cubic feet
BOE means barrels of oil equivalent
MMBOE means millions of barrels of oil equivalent
MMSCFPD means millions of standard cubic feet per day
End of this Release
ADX Energy Ltd | ABN 50 009 058 646 -Registered and Principal Office Australia
29 Bay Road, Claremont WA 6010, Australia
Telephone: +61 8 9381 4266 | admin@adxenergy.com.au | adxenergy.com.au
Page | 4
Share your feedback
Discover