Welchau Investment Agreement Amendment
Released
Released
Announcement PDF
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
9 January 2024
Welchau Investment Agreement
Amendment
MCF Energy increases Welchau-1 well funding obligation from 50%
of EUR 3.8 million to 50% of EUR 5.1 million for an increase in
economic interest from 20% to 25%
Key points:
In early 2023, Canadian TSX Venture Exchange listed MCF Energy Ltd. (MCF), executed
an Energy Investment Agreement (EIA) to fund 50% of the cost of the Welchau-1
exploration well to earn a 20% economic interest in the Welchau Investment Area. The
funding obligation was based on a well cost cap of EUR 3.8 million.
Additional permitting costs to secure an environmental clearance and additional pre-drill
costs including the drilling of a shallow geotechnical and water well has resulted in an
increase in well costs from EUR 3.8 million to EUR 5.1 million.
MCF and ADX have agreed to vary the terms of the EIA such that MCF will fund 50% of
the Welchau-1 well costs up to EUR 5.1 million to earn a 25% economic interest in the
Welchau Investment Area. MCF and ADX will pay their economic interest share of Welchau
Investment Area related costs of 25% and 75% respectively once the revised well cost cap
has been reached.
Drilling operations are expected to commence upon completion well site construction in
late January and mobilisation the RED Drilling & Services GmbH (RED) E-202 drilling rig
to the Welchau-1 drilling location.
The Welchau-1 exploration well is located in the Welchau Investment Area in ADX’ ADXAT-II licence in Upper Austria.
The Welchau gas prospect has exceptional gas resource potential, located in the heart of Europe at a
relatively shallow drill depth and proximal to gas pipelines. ADX estimates that Welchau has best
technical Prospective Resources of 807 BCFE (134 MMBOE) 1. Welchau is targeting the same
reservoirs as the nearby Molln-1 well which tested gas in 1989.
Prospective Resources are those estimated quantities of petroleum that may potentially be recovered
by the application of a future development project(s) related to undiscovered accumulations. These
estimates have both an associated risk of discovery and a risk of development. Further exploration
appraisal and evaluation is required to determine the existence of a significant quantity of potentially
moveable hydrocarbons.
ADX Executive Chairman, Mr Ian Tchacos, said, “The Board of ADX looks forward to the
imminent drilling of the Welchau-1 well. The amendment to the EIA reduces ADX exposure to
increased well costs for a modest and commensurate decrease in economic interest to 75%.
The Welchau exploration project is an exceptional domestic energy supply and economic
opportunity for the State of Austria. ADX and our partner MCF are committed to pursuing
responsible gas exploration at a time when energy security is of critical importance in Europe”.
¹ Best Technical Prospective Resources Prospective resources reporting date 22.06.2023
ADX Energy Ltd | ABN 50 009 058 646 -Registered and Principal Office Australia
29 Bay Road, Claremont WA 6010, Australia
Telephone: +61 8 9381 4266 | admin@adxenergy.com.au | adxenergy.com.au
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
ADX Energy Ltd (ASX Code: ADX) entered into an Energy Investment Agreement on the 2nd of January 2023
(EIA) for the Welchau Investment Area with Canadian TSX Venture Exchange (TSXV) listed MCF Energy Ltd.
(TSXV – MCF.V) (MCF). Under the terms of the EIA, MCF (via its’ subsidiary MCF Energy GmbH) agreed to
fund 50% of the Welchau-1 well drilling costs up to a maximum of EUR 3.8 million (Well Cap) to earn a 20%
economic interest in the Welchau Investment Area.
ADX and MCF have agreed to vary the EIA whereby MCF will fund 50% of the Welchau-1 well drilling costs up
to a maximum of EUR 5.1 million (Revised Well Cap) to earn a 25% economic interest in the Welchau
Investment Area (instead of a 20% economic interest). MCF and ADX will pay their economic interest share of
Welchau Investment Area costs of 25% and 75% respectively once the Revised Well Cap cost has been
reached.
The increase in estimated well costs from EUR 3.8 million to EUR 5.1 million is the result of additional permitting
costs to secure an environmental clearance, drilling cost escalation and additional pre-drill costs including the
drilling of a shallow geotechnical and water well.
The Welchau-1 exploration well is located in the Welchau Investment Area in ADX’ ADX-AT-II licence in Upper
Austria. ADX is operator of the ADX-AT-II licence and the Welchau Investment Area.
Welchau-1 Well Operations
Well site construction commenced on the 15th of December 2023 following receipt of an environmental clearance
from the Department of Nature Protection of the State Government of Upper Austria to drill the Welchau-1 gas
well. The environmental clearance was the last regulatory approval required to commence drilling operations
on the Welchau prospect. The environment clearance followed a drilling permit for the well that was received
from the Mining Authority on behalf of the Ministry of Finance of the Republic of Austria.
Drilling operations at Welchau are expected to commence in late January 2024 following the completion of well
site construction and the mobilisation of the RED Drilling & Services GmbH E-202 drilling rig which has recently
been used for drilling of the Anshof-2 well and the Anshof-3 discovery well. ADX has maximised local content
where there is an excellent past record of safety, environmental protection and project execution. The success
case drilling program is expected to take approximately 39 days.
Welchau Investment Area Economic Interests
ADX holds a 75% economic interest in the Welchau Investment Area which contains Welchau Gas Prospect and
other emerging gas prospects in ADX’ ADX-AT-II licence in Upper Austria. MCF Energy Ltd. (TSXV – MCF.V)
(via its’ subsidiary MCF Energy GmbH) has executed an Energy Investment Agreement to fund 50% of the
Welchau-1 well costs up to a well cost cap of EUR 5.1 million to earn a 25% economic interest in the Welchau
Investment Area.
For further details please contact:
Paul Fink
Ian Tchacos
Chief Executive Officer
Executive Chairman
+61 (08) 9381 4266
+61 (08) 9381 4266
paul.fink@adx-energy.com
ian.tchacos@adxenergy.com.au
Authorised for lodgement by Ian Tchacos, Executive Chairman
Page | 2
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
Persons compiling information about Hydrocarbons:
Pursuant to the requirements of the ASX Listing Rule 5.41 the technical and Prospective Resources information
relating to Austria contained in this release has been reviewed by Paul Fink as part of the due diligence process
on behalf of ADX. Mr. Fink is Technical Director of ADX Energy Ltd is a qualified geophysicist with 30 years of
technical, commercial and management experience in exploration for, appraisal and development of oil and gas
resources. Mr. Fink is a member of the EAGE (European Association of Geoscientists & Engineers) and FIDIC
(Federation of Consulting Engineers).
Previous Estimates of Reserves and Resources:
ADX confirms that it is not aware of any new information or data that may materially affect the information
included in the relevant market announcements for reserves or resources and that all material assumptions and
technical parameters underpinning the estimates in the relevant market announcements continue to apply and
have not materially changed.
Reporting Standards for Resource Estimation
Reserves and resources are reported in accordance with the definitions of reserves, contingent resources and
prospective resources and guidelines set out in the Petroleum Resources Management System (PRMS) prepared
by the Oil and Gas Reserves Committee of the Society of Petroleum Engineers (SPE) and reviewed and jointly
sponsored by the American Association of Petroleum Geologists (AAPG), World Petroleum Council (WPC),
Society of Petroleum Evaluation Engineers (SPEE), Society of Exploration Geophysicists (SEG), Society of
Petrophysicists and Well Log Analysts (SPWLA) and European Association of Geoscientists and Engineers
(EAGE), revised June 2018.
Prospective Resource Classifications
Low Estimate scenario of Prospective Resources - denotes a conservative estimate of the quantity that will
actually recovered from an accumulation by an oil and gas project. When probabilistic methods are used, there
should be at least a 90% probability (P90) that the quantities actually recovered will equal or exceed the low
estimate.
Best Estimate scenario of Prospective Resources - denotes the best estimate of the quantity that will actually be
recovered from an accumulation by an oil and gas project. It is the most realistic assessment of recoverable
quantities if only a single result were reported. When probabilistic methods are used, there should be at least a
50% probability (P50) that the quantities actually recovered will equal or exceed the best estimate.
High Estimate scenario of Prospective Resources - denotes an optimistic scenario of the quantity that will
actually be recovered from an accumulation by an oil and gas project. When probabilistic methods are used, there
should be at least a 10% probability that the quantities actually recovered will be equal or exceed the high
estimate.
End of this Release
Page | 3
Share your feedback