Company Presentation - Sicily Channel Permit, Offshore Italy
Released
Released
Announcement PDF
E U R O P E A N
F O C U S S E D
ENERGY
P R O D U C E R
&
E X P L O R E R
Company Presentation – Sicily Channel Permit, Offshore Italy
“A New Gas Frontier at Europe’s Door-Step”
Presented by:
• Ian Tchacos - Executive Chairman
• Paul Fink – Chief Executive
• Giuseppe Rigo – Italy Manager
• Paolo Pace – Italy Geoscience Advisor
On 11 September 2025
A S X : A D X
DISCLAIMER (CAUTIONARY STATEMENT)
IMPORTANT NOTICE:
This document has been prepared by ADX Energy Ltd (“ADX”) for the purpose of providing information to
interested analysts, investors and shareholders. Any statement, opinions, projections, forecasts or other
materials contained in this document do not constitute any commitments, representations or warranties by ADX
or its directors, agents and employees.
Except as required by law, and only to the extent so required, directors, agents and employees of ADX shall in no
way be liable to any person or body for any loss, claim, demand, damages, costs or expenses of whatsoever
nature arising in any way out of, or in connection with, the information contained in this document. This
document includes certain statements, opinions, projections, forecasts and other material, which reflect various
assumptions. The assumptions may or may not prove to be correct. ADX recommends that potential investors
consult their professional advisor(s) as investment in the company is considered to be speculative in nature.
The information in this presentation is in summary form only and does not contain all the information necessary
to fully evaluate any transaction or investment. It should be read in conjunction with ADX’ other periodic and
continuous disclosure announcements lodged with the ASX. This document does not constitute an offer,
invitation or recommendation to subscribe for or purchase securities and does not form the basis of any contract
or commitment.
Pursuant to the requirements of the ASX Listing Rule 5.41 and 5.43 the technical and Prospective Resources
information relating to Austria and Italy contained in this presentation has been reviewed by Paul Fink as part of
the due diligence process on behalf of ADX. Mr. Fink is Technical Director of ADX Energy Ltd is a qualified
geophysicist with 30 years of technical, commercial and management experience in exploration for, appraisal
and development of oil and gas resources. Mr. Fink is a member of the EAGE (European Association of
Geoscientists & Engineers) and FIDIC (Federation of Consulting Engineers). ADX confirms that it is not aware of
any new information or data that may materially affect the information included in the relevant market
announcements for reserves or resources and that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcements continue to apply and have not materially
changed.
Independent audit of developed reserves have been completed for ADX’ Zistersdorf and Gaiselberg fields
(“Fields”) in the Vienna basin and Anshof in Upper Austria (Austria) by RISC Advisory Pty Ltd (“RISC”). RISC
conducted an independent audit of ADX’ Fields evaluations, including production forecasts, cost estimates and
project economics. Production from existing wells is classified as Developed Producing. Production from planned
recompletion of existing wells to new intervals is classified as Developed Non-Producing. RISC is an independent
advisory firm offering the highest level of technical and commercial advice to a broad range of clients in the
energy industries worldwide. RISC has offices in London, Perth, Brisbane and South-East Asia and has completed
assignments in more than 90 countries for over 500 clients and has grown to become an international energy
advisor of choice.
PRMS RESERVES CLASSIFICATIONS USED IN THIS PRESENTATION:
Developed Reserves are quantities expected to be recovered from existing wells and facilities.
Developed Producing Reserves are expected to be recovered from completion intervals that are open and
producing at the time of the estimate.
Developed Non-Producing Reserves include shut-in and behind-pipe reserves with minor costs to access.
Undeveloped Reserves are quantities expected to be recovered through future significant investments.
A. Proved Reserves (1P) are those quantities of Petroleum that by analysis of geoscience and engineering data,
can be estimated with reasonable certainty to be commercially recoverable from known reservoirs and under
defined technical and commercial conditions. If deterministic methods are used, the term “reasonable certainty”
is intended to express a high degree of confidence that the quantities will be recovered. If probabilistic methods
are used, there should be at least a 90% probability that the quantities actually recovered will be equal or
exceed the estimate.
B. Probable Reserves are those additional Reserves which analysis of geoscience and engineering data indicate
are less likely to be recovered than Possible Reserves. It is equally likely that actual remaining quantities
recovered will be greater than or less than the sum of the estimated Proved plus Probable Reserves (2P). In this
context, when probabilistic methods are used, there should be at least a 50% probability that the actual
quantities recovered will equal or exceed the 2P estimate.
C. Possible Reserves are those additional Reserves that analysis of geoscience and engineering data suggest are
less likely to be recoverable that Probable Reserves. The total quantities ultimately recovered from the project
have a low probability to exceed the sum of Proved plus Probable plus Possible (3P) Reserves, which is equivalent
to the high-estimate scenario. When probabilistic methods are used, there should be at least a 10% probability
that the actual quantities recovered will equal or exceed the 3P estimate. Possible Reserves that are located
outside the 2P area (not upside quantities to the 2P scenario) may exist only when the commercial and technical
maturity criteria have been met (that incorporate the Possible development scope). Standalone Possible Reserves
must reference a commercial 2P project.
PROSPECTIVE RESOURCE CLASSIFICATIONS USED IN THIS PRESENTATION:
Prospective Resources are those estimated quantities of petroleum that may potentially be recovered by the
application of a future development project(s) relate to undiscovered accumulations. These estimates have both
an associated risk of discovery and a risk of development. Further explorations appraisal and evaluation is
required to determine the existence of a significant quantity of potentially moveable hydrocarbons.
P(90) Estimate or Low Estimate: means at least a 90% probability that the quantities actually recovered will
equal or exceed the estimate.
P(50) Estimate or Best Estimate: means At least a 50% probability that the quantities actually recovered will
equal or exceed the estimate.
P(10) Estimate or High Estimate: means At least a 10% probability that the quantities actually recovered will
equal or exceed the estimate.
OIL AND GAS CONVERSIONS
BOE means barrels of oil equivalent. Bcfe means billion of cubic feet of gas equivalent. Gas to oil conversion used
in this presentation: 6 Mcf of gas = 1 barrel of oil. Mcf means thousand cubic feet of gas
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
2
INVESTMENT PROPOSITION AND OPERATING STRATEGY
A COMPELLING PORTFOLIO: STABLE PRODUCTION, LOW-RISK IMMEDIATE GROWTH AND HIGH IMPACT EXPLORATION
Austrian
Long Term
Production
303 BOEPD 1
Austrian
Exploration
Portfolio
374 BCF Gas
31 MMBBL Oil 2
New Italian
Growth
Portfolio
369 BCF Gas 3
Value Adding
Renewable
Projects
Solar &
Geothermal
Operating
Capability
Generate,
Explore &
Develop
Multiple
Farmouts
Accelerate
programs &
reduce risk
CAUTIONARY STATEMENT: Prospective Resources are those estimated quantities of petroleum that may potentially be recovered by the application
of a future development project(s) relate to undiscovered accumulations. These estimates have both an associated risk of discovery and a risk of
development. Further explorations appraisal and evaluation is required to determine the existence of a significant quantity of potentially moveable
hydrocarbons.
1 Quarter 2 2025 average Austrian net production. 2 Prospective Resources reporting date update 27.8.2025 (refer slide 17). 3 Prospective Resources reporting date update 30.8.2022
“Stable production, boots on the ground and an asset rich
portfolio providing multiple opportunities for growth”
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
3
GEOGRAPHY, FINANCE AND STRATEGIC POSITION
Capital Structure
01
Ticker
ASX: ADX
FRA: GHU
Share Price (at 25 August 2025)
A$0.031
Number of shares
584m
Number of options
94m
Market capitalisation
A$18.1M
Cash (unrestricted) at 30 June 2025
A$4.8M
02
Debt
A$1.3M
Enterprise value
A$14.6M
Number of shareholders
1,936
Upper Austria Production
& Exploration
Vienna Basin
Oil Fields
Romania Pannonia
Licences
Strategic European Presence
• Operating in Tier 1 jurisdictions: Austria,
03
•
•
•
Italy, and Romania
Extensive Well and Seismic Data Base
Exposure to Brent oil and premium
European gas markets
Excellent access to established energy
infrastructure
Sicily Channel Gas
Exploration Permit
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
4
RECENT ACTIVITIES AND RESULTS
SUMMARY OF RESULTS – Q2 2025
Current Quarter
Previous Quarter
% age Change
303
246
+23%
US$67.82
US$75.66
- 10%
Sales Revenue
A$ 2.6 million 1
A$ 2.5 million
+4%
Cash Unrestricted
A$ 4.8 million 1, 2
A$ 6.7 million 2
-28%
Net Production Rate (BOEPD)
Average Oil Price Brent (US$/bbl)
1 Includes only 2 months of sales - excludes payment of A$ 0.7 million received on 1 July 2025
2 Excludes restricted funds secured for bonds and guarantees totalling A$ 1.2 million
Recent Activities
Permitting and drill sites for three shallow gas wells in Upper Austria
Purchased an additional 20% economic interest in Anshof Field Area
Welchau-1 testing remains on hold due to environmental objection
Sicily Channel Gas Exploration Permit Award – August 2025
Upper Austria Prospect Inventory Update
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
5
FAVOURABLE OPERATING POSITIONS IN AUSTRIA AND ITALY
“Highly prospective, Short exploration time-lines; high value hydrocarbons and rapid development cycles ”
Infrastructure Access excellent for oil and gas in Austria; excellent for gas in Italy’s Sicily Channel
Energy Demand high demand for both gas and oil, with heavy reliance on gas and oil imports in Austria and Italy gas price at approx. EUR 33.3 per MWh (US$11.7 per MCF) 3.9 times higher than in the USA
Data Availability 3,500 Km2 3D seismic plus basin wide well data base in Upper Austria; high quality 2D data set
and well data from historic oil exploration in permit in Sicily Channel
Operating Environment pro-development, rapid permitting, ADX only 3rd operator in Austria; pro-development
centre right government, strong focus on gas and very low royalty rates (10%) in Italy
Vienna
Basin Fields
Austria
ADX Sicily
Channel
Permit
Anshof
Oil Field
ADX-AT-I
licence
ADX-AT-II
licence
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
6
NEAR-TERM ACTIVITIES – VALUE DEVELOPMENT CATALYSTS
Q4 2025
Shallow Gas Drilling Upper Austria
Farmout GOLD Prospect
Permitting and Rig Contracting
Drill 2 firm wells plus an optional well
Anshof Near Field Oil Appraisal
Well Permitting and land access
Further drill target maturation
Drill oil appraisal well
Welchau Testing & Follow Up Exploration
Welchau-1 ongoing testing 1
Ongoing maturation and farmout of
Rossberg and Welchau Deep Prospects
Sicily Channel Permit
Buy new seismic & update resources
Independent Resources Review
Seismic Reprocessing & Farmout
1 Welchau-1 testing remains suspended due to environmental objection
Q1 2026
Q2 2026
A low risk, high
value pathway to
new cash flow
High value
additional oil tie-in
to Anshof facility
Company
transforming
hydrocarbon play
High-value gas
potential in prime
location
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
7
SICILY CHANNEL “C.R150. AU” PERMIT, OFFSHORE ITALY
Presentation Agenda
1. Italy Energy Background – Giuseppe Rigo
2. Sicily Channel Exploration and Production History – Paulo Pace
3. Permit Gas Play and Proven Analogies
4. Permit Data Availability and Prospectivity Assessment – Paul Fink
5. Planned Forward Work Program
6. Indicative Potential in Case of Success– Ian Tchacos
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
8
ITALY ENERGY BACKGROUND
Political System
• Italy is a parliamentary republic, with a multi-party system, led by a prime minister (Giorgia
Meloni), appointed by the President of the Republic (Sergio Mattarella)
• Most of the Italian government’s activity has been focused on economic recovery. Italy's economy
grew, with a 0.4% increase in GDP in Q2 2025. The fiscal deficit narrowed to 3.4% of GDP in 2024,
down from 7.2% in 2023
• In the E&P sector, Parliament is working to simplify authorization processes and accelerate the
start-up of gas fields production (e.g. Argo-Cassiopea and Longanesi)
Gas Supply and Demand
• Italy has a high natural gas demand but low domestic production, making it heavily reliant on
imports. Net Italian gas imports has been stable since 2021 at around 95%
• Italy generates 45% of its electricity from natural gas with only 5% of gas demand covered by
domestic production
• In 2024, Italy's natural gas production reached the record low of 2.88 billion cm while the country’s
consumption reached some 58.9 billion cm
• Increased domestic production provides energy security and offers the opportunity to lower Italian
power prices (among the highest In Europe)
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
9
ITALY ENERGY BACKGROUND (CONTINUED)
Licencing
• Exploration permits are of six years initial length, with two possible renewals for three years
each
• Granting requires EIA’s approval from the Ministry of the Environment
• Entitles holder to carry out any kind of geological and geophysical survey. Drilling of one
well is the minimum commitment required
• Exploration permits are exclusive and can be awarded to a single title holder or to a group
of companies (who must appoint an operator)
Fiscal Terms and Royalties
• The corporate income tax rate, IRES, for oil and natural gas companies is 27.5%
• There are a number of allowances on exploration and development spending and deductions
are allowed for surface rental fees and royalties
• Operating costs are written-off the year in which they are incurred
• Intangible assets are generally depreciated over five years with a few exceptions
• A 10% royalty is charged for offshore gas production
• Royalties not charged when production is lower than 80 million cm per field per year
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
10
ITALY ENERGY BACKGROUND (CONTINUED)
Sicily Channel Infrastructures
The Trans-Mediterranean Pipeline (TransMed) is a natural gas pipeline from
Algeria via Tunisia to Sicily and then to mainland Italy. An extension of the
TransMed pipeline delivers Algerian gas to Slovenia
The C.R150.AU permit
is located
approximately 50 km
from a potential gas tie
in point onshore near
Lippone-Mazara gas
field
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
11
EXPLORATION AND PRODUCTION HISTORY - NILDE OIL FIELD
•
Re-development of the prematurely
abandoned Nilde Oil Field (Agip-ENI 1973
discovery) which previously produced 20.5
MMbbl of 39° API oil in the 80s from the
Nilde Fm. reefal fractured carbonates of
Middle Miocene Serravallian age
•
Ramped production up to 12,100 bopd from
Nilde-2 and 6 close-by wells
•
The field was shut-in from 1989 as economic
conditions in a low oil price environment
were unfavourable to continued development
•
Large remaining oil contingent resources
•
Additional potential from Naila and Norma
discoveries and 5 exploration leads
•
Former d 363 C.R-.AX application for
exploration license awarded as C.R150.AU
exploration permit in August 2025
ADX CPR (2018)
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
12
EXPLORATION AND PRODUCTION HISTORY - SICILY GAS E&P OVERVIEW
•
C.R 150.AU Exploration license (345.90
km2) in marine Zone C with Nilde oil field,
proven shallow biogenic gas and several
gas and oil leads/prospects (water depth
70-130 m)
•
G.C 1.AG Production license (ENI
Mediterranea Idrocarburi 60% - Energean
Italy 40%) with Argo-Cassiopea gas fields,
Gemini gas discovery and gas prospects
•
G.R 14.AG Exploration license (ENI
Mediterranea Idrocarburi 60% - Energean
Italy 40%) with Panda gas field and several
gas prospects
•
G.R 13.AG Exploration license (ENI 60% Energean Italy 40%) with several gas
prospects
•
LIPPONE-MAZARA Production license (ENI
Mediterranea Idrocarburi 100% with
Lippone-Mazara gas field representing the
direct analogue to the C.R150.AU gas
prospects
/discovery
/discovery
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
13
EXPLORATION AND PRODUCTION HISTORY - ARGO-CASSIOPEA FIELDS
•
Production started in August 2024 from Argo-Cassiopea
(2007-08 ENI discoveries) fields located 30 km off the SW
Sicily coast in a water depth of 550-620 m
•
10 Bcm (353 bcf) of reserves (ENI) declared as the biggest
offshore gas (99% CH4) field in Italy
•
Expected peak production 1.5 bcm per year (9.2 Mmboe/d)
about 2.3 Mmboe/d per well
•
Biogenic gas play in structural-stratigraphic traps over preexisting structural highs within the Plio-Pleistocene
sediments of the Gela foredeep
•
Development through 4 subsea
wells (2 new wells and 2 recompletions) tied back to the
Prezioso K platform which hosts
the treatment and compression
system and natural gas is
transported via a 14in 60km-long
pipeline to the Gela processing
plant
From Energean website
From ENI brochure
From ENI documentation
presented for VIA
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
14
EXPLORATION AND PRODUCTION HISTORY - GEMINI DISCOVERY
•
Gemini-1 exploration well drilled
in late 2024 by the Saipem 10000
drilling ship within the production
concession G.G 1.AG
•
Gas discovery within the Gemini
3D-amplitude anomaly supported
prospect located a few km south
of Argo-Cassiopea gas fields
•
Drilled in a water depth of about
705 m penetrating several stacked
gas-bearing sandstone reservoirs
(up to 35% porosity) across a 400
m-thick sequence
•
Declared GIIP like the Argo field
(≈100 bcf)
•
Total GIIP of Gemini with ArgoCassiopea reaches about 600 bcf
with good recovery factors (up to
75%)
From Assorisorse Exploration Scout Group June 2025
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
15
EXPLORATION AND PRODUCTION HISTORY - ADX OFFSHORE TUNISIA-ITALY PAST
EXPLORATION ACTIVITIES
•
Large dual-sensor 3D survey acquired by ADX in 2010 with
PGS dual-sensor technology (Geostreamer) over the Dougga
condensate and Lambouka gas fields
•
Excellent imaging of the Miocene and Pliocene foredeeps
and associated gas plays with pinch-outs and mixed
structural-stratigraphic traps
Possible trapped gas
Fink et al. (2012)
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
16
EXPLORATION AND PRODUCTION HISTORY - LIPPONE-MAZARA GAS FIELD
•
Lippone-Mazara biogenic gas field located onshore SW Sicily (ENI 100%)
•
Discovered in 1960 by Agip recovered 82.01% of its total recoverable reserves with
peak production in 1988
•
Based on economic assumptions production will continue until the field reaches its
economic limit in 2057
•
Source/Seal: shales and argillites of the Terravecchia Fm.
•
Reservoir: late Tortonian (upper Miocene) turbiditic sandstones of the Terravecchia
Fm. (porosity up to 33%)
•
Trap: thrust-related folds and pop-up structures
•
HC type: biogenic gas methane (99% CH4)
TERRAVECCHIA
Catalano et al. (2002)
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
17
•
Working biogenic gas system also testified by several
gas shows reported from various wells drilled onshoreoffshore Sicily (e.g., Poggioreale-1, Corvi-1, Onda-1,
Orlando-2, Nilde-2, …)
•
Source/Seal: shales and argillites of Terravecchia Fm.
•
Reservoir: late Tortonian (upper Miocene) turbiditic
sandstones and conglomerates (porosity up to 33%)
•
Trap: mixed structural-stratigraphic traps over
structural highs and pinchouts
•
HC type: biogenic gas methane (expected to be 99%
CH4 like Lippone-Mazara gas field analogue)
TERRAVECCHIA
Biogenic gas play within the siliciclastic foredeep
sequence of the Upper Tortonian- Lower Messinian
Terravecchia Fm. proven by Lippone-Mazara gas field
500 msec
•
TERRAVECCHIA
PERMIT GAS PLAY & PROVEN ANALOGIES - C.R 150.AU GAS PLAY TYPE
R
R
R
TERRAVECCHIA
OUTCROP EXAMPLES
Play Type Example
Lentini & Carbone (2014)
Modified from Casero (2004)
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
18
PERMIT GAS PLAY & PROVEN ANALOGIES - NILDE-2 GAS SHOWS
•
Strong gas shows reported from the Nilde 2 (first Nilde oil field production well drilled in 1976)
well within the Tortonian-Messinian Terravecchia Fm.
•
AC-80 seismic line (2015 purchase from ENI) across the Nilde-2 well showing the HC potential
Gas shows in the
Terravecchia Fm.
Udrained
compartment
Produced ≈20 MMbbl
oil compartment
NILDE-2
TERRAVECCHIA
NILDE-2
Line AC-80
Top Nilde
Reservoir
Nilde 2
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
19
PERMIT GAS PLAY & PROVEN ANALOGIES - 3D SEISMIC IMPROVES PROSPECTIVITY
LEGACY 2D LINE 80s ACROSS CASSIOPEA FIELD
NEW 3D SHOWING CASSIOPEA FIELD AND VELA PROSPECT
G-82-134
ViDEPI Database
From ENI documentation presented for VIA
•
Legacy seismic line versus new 3D seismic showing the same setting across the Argo-Cassiopea fields
•
The 3D data highlight the amplitude anomalies of the stacked gas-bearing reservoirs that cannot be detected on the
legacy seismic
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
20
DATA AVAILABILITY- PURCHASED FOR NILDE OIL FIELD EVALUATION (2016)
Detailed well data & core
data acquired from ENI
Nilde oil production & reserves data
Seismic data review & purchase from
ENI who acquired seismic from 1973 to
1992
ADX 2D seismic Carbonate reservoir
interpretation & new reserves / resources
Fractured reservoir (Miocene – Serravallian)
future productivity & economics analysis
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
21
PROSPECTIVITY ASSESSMENT - NEW GOVERNMENT & LICENSE OFFER IN 2022
•
After 2019 moratorium of offshore and onshore
exploration (refer ASX 4th Feb. 2019) the new
government offered ADX in 2022 a revised
d363C.R-AX area, conditional on gas exploration
only and a slightly reduced area.
•
In order to ratify the license, the new
government requested ADX to provide technical
& commercial information.
•
Given the detailed technical work within both
the d363C.R-AX area and the relatively close by
Pantelleria area (ADX dual sensor 3D seismic in
combination with its previous Tunis “Kerkouane”
area)) ADX could provide a natural (biogenic) gas
potential report to the Italian Authorities in a
short amount of time.
•
1
2025 final area award: 345.90 km2
2022 revised area proposal
Initial d363 area
1, 2
2019 suspension & area
reduction
In August 2025 the Italian Ministry of
Environment and Energy Security awarded the
C.R150.AU Exploration Permit (“Permit”) to ADX.
Refer to Cautionary Statement in slide 3 of this presentation
2 Prospective Resources reporting date update 30.8.2022
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
22
DATA AVAILABILITY - GAS PROVEN IN A LARGE AREA WITHIN SIMILAR RESERVOIRS
1. ADX C.R 150.AU well data & 2D
seismic clearly proves high porosity
Miocene sandstone and gas (2D DHI)
2
1
1: ADX -- C.R 150. AU
3: Several Miocene gas
sandstone reservoirs in onshore
wells, close to Lippone
3: Onshore Sicily
Several strong gas
kicks : Kerk-1
Nilde oil
production
3
2: Tunisia & Pantelleria
4: Latest 3D not only proofs gas
reservoirs but with extremely
high resolution also a very large
number of sandstone reservoirs
3
1
3: ENI – 2024 Production start
2
2: Tunisia & Pantelleria: Miocene &
Pliocene high porosity shallow gas
sandstones proven in wells (Kerkouane 1a) and ADX 3D seismic 770 km2
4
4
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
23
PLANNED WORK PROGRAM - KEY NEAR TERM ACTIVITIES & EXPECTED RESULTS
ADX will increase the historically acquired 2D seismic dataset via purchases
from several companies, mainly ENI
Modern Seismic reprocessing is expected to significantly improve resolution
and hence the proof a larger number of stacked reservoirs in future wells
In addition to the past well data purchase close to the Nilde oil field, more
data from other wells will be obtained. The main objective is to further (as
was the case in Nilde-2) investigate already proven shallow gas reservoirs
STRAT TRAPS LEADS TO
BECOME NEW PROSPECTS
AND HENCE ADDITIONAL
RESOURCES
Seismic reprocessing will increase
resolution and hence number of
potential stacked reservoirs
o Greater number of stacked reservoirs per prospects, as demonstrated in
the recently acquired 3D seismic data by ENI and ADX
o Larger prospective resources: The current best technical prospective
resources of 369 bscf 1, 2 for 5 prospects are based on a relatively small
number of assumed reservoirs. 2D reprocessing could prove several
additional gas reservoirs, in line with the very recent ENI and ADX 3D
seismic
TERRAVECCHIA
The key expected results are:
o Additional prospects, especially stratigraphic – pinch out traps to be
identified on more seismic data
o More well (logging) data and petrophysics are likely to prove even higher
porosity and reserves per gas reservoir than currently assumed.
1
Refer to Cautionary Statement in slide 3 of this presentation
2 Prospective Resources reporting date update 30.8.2022
Strat trap leads and hence pinch out
position could be clearly defined with
reprocessing
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
24
PLANNED WORK PROGRAM - FURTHER ACTIVITIES & RESULTS
•
Gas resources and chance of success (COS) of existing and new potential prospects should be identified after the
reinterpretation of reprocessed 2D seismic data independently reviewed by international experts. Based on the
interpreted high quality gas reservoirs and improved seismic resolution the geological chance of success is expected to
be high. It is possible that the Best Case Estimates for the 5 prospects in the Permit may trend toward the upside High
Case Estimates evaluated on the 30 August 2022 due to a significant increase in the number of stacked reservoirs
incorporated and higher porosities than previously assumed.
•
In collaboration with independent experts an area with the largest number of prospects, resources and COS will be
selected for future 3D seismic. Currently at least around 150 km2 of 3D seismic coverage area is expected.
•
It is expected that after the Permit wide prospective resources will be updated based on additional purchased 2D
seismic and well data, that several companies will show farmin interest. 3D seismic acquisition will be targeted with a
potential farminee. The combined objective will be to drill the first exploration well within the next 3 years.
Prospective Resources Estimates
ADX
Interest
1
100%
2
100%
3
100%
4
100%
5
100%
Arithmetic Total (BCF)
Prospect
Number
(in Billion cubic feet)
Low
Best
Case
Case
20
62
21
70
25
106
11
42
27
90
369
103
High
Case
124
142
233
88
184
772
1,2,3
ASX Reporting
Date
30-Aug-22
30-Aug-22
30-Aug-22
30-Aug-22
30-Aug-22
New 3D seismic
compared to
old 3D
significantly
increases predrill resources
estimates
[1]
Prospective Resource Estimates are unrisked recoverable. They have been
estimated using probabilistic methodology in accordance with SPE-PRMS (2018).
[2]
Best Case estimates reported on 30 August 2022, High and Low estimates reported
for the first time on 11 September 2025
3 Refer to Cautionary Statement in slide 3 of this presentation
ADX Energy (ASX: ADX) | Investor Presentation – Sicily Channel Webinar | 11 September 2025
25
INDICATIVE POTENTIAL IN CASE OF SUCCESS – 300 BCF SCENARIO 1
Key Project Attributes
Shallow water – 100 m compared to 700 m at ENI’s Argo
Cassiopea field
Shallow to moderate drill depths 600m to 1600m
Subsea wells and tie back to shore
Onshore plant and open access to pipelines
Clean biogenic gas and productive reservoirs
Favourable fiscal terms and high gas price
Indicative Capital Costs
US$ 000
Exploration and development wells
Subsea well heads, manifold,
umbilicals and control systems
Subsea pipeline
Onshore gas plant
Engineering and insurance
$
135,000
$
$
$
$
80,000
60,000
55,000
50,000
Total Capex (US$ 000)
$
380,000
Development Assumptions for Subsea Project
4 exploration wells with 2 completed as producers
6 development wells completed subsea
Approx. 50 BCF per well and 15 MMCFPD
3 fields tied in via subsea manifold to 300 mm subsea
pipeline