Anshof-2 Appraisal Well Update
Drilling Operations Report No 5
Wireline logging results indicate a much larger high quality reservoir intersection at or near
the field oil water contact.
The shallower than predicted oil water contact is compensated by the flattening of the
structure increasing up-dip volume and the existence of a much thicker reservoir
intersection which has been confirmed to extend across the field.
ADX and its partner MND have decided to suspend the well with the intention of side tracking
the well to an up-dip location after the drilling of the ADX Welchau-1 well.
Key points:
The Anshof-2 well has intersected the predicted Eocene oil reservoir section at a depth of approximately
2160 metres measured depth (MD), approximately 40 to 50 metres higher than prognosis in terms of vertical
depth. The well was directionally drilled in 8 ½ inch hole to a total measured depth of 2321 metres (TMD)
with a final inclination of approximately 73° (i.e. near horizontal). The well has been evaluated with electric
wireline logs.
Preliminary petrophysical analysis of the Eocene sands confirms at least 12 metres net vertical thickness
of high quality reservoir with a porosity of approximately 20%, significantly surpassing the reservoir quality
and thickness found in the Anshof-3 discovery well located to the West that has demonstrated strong
production performance. The calculated oil saturation across the interval is approximately 34% and as a
result the well will not be completed as an oil producer at this bottom hole location but suspended for
deviation to a yet to be finalised up-dip location. Oil shows (fluorescence and good chloroform test reaction)
at the top of the Eocene section indicate that higher oil saturations can be expected slightly further up-dip
from the Anshof-2 bottom hole location. Refer to figure 2.
While the oil saturation at the Anshof-2 bottom hole location is clearly less than expected, ADX’ interpretation
is that the well has penetrated the Eocene reservoir close to the oil water contact (OWC). The presence of
a thick very high-quality reservoir section in line with ADX’ P10 (upside) case pre drill maps and the fact that
Anshof oil field structure is flatter and larger due to the Eocene sands being encountered 40 to 50 metres
higher than prognosis is expected to compensate for the shallower than expected OWC depth at this
location, i.e. a larger crestal volume with greater net reservoir thickness (approx. 5 times that encountered
at the Anshof-3 discovery and production well).
The suspension of the Anshof-2 well allows the time to evaluate an optimal well location which is sufficiently
up-dip from the current bottom hole location with an intersection of a similar or greater thickness of highquality reservoir sandstones. The drilling of a side track from the bottom of 9 ⅝ inch casing provides
significant cost savings for the planned sidetrack development well (refer to figure 1).
Eocene oil production wells in the basin with similar high quality sand intersections as encountered in
Anshof-2 have produced at rates of approximately 1,000 barrels per day.
The Anshof-2 appraisal well is located in the ADX-AT-II licence in Upper Austria. The well was spudded at
10:00 am Central European Time (CET) on the 13th of November 2023. ADX is the operator and has a 60%
economic interest in the well. The RED Drilling & Services GmbH (RED) E-202 drilling rig is expected to be
released on the 12th December 2023 following completion of suspension operations.
ADX Energy Ltd | ABN 50 009 058 646 -Registered and Principal Office Australia
29 Bay Road, Claremont WA 6010, Australia
Telephone: +61 8 9381 4266 | admin@adxenergy.com.au | adxenergy.com.au
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
ADX Energy Ltd (ASX Code: ADX) advises that the Anshof-2 well has been directionally drilled in 8 ½ inch hole
to a total measured depth of 2321 metres (TMD) with a final well bore inclination of approximately 73°. The well
has been evaluated with electric wireline logs (Logging) and is currently being suspended for future side track
as a producer in the near future.
The well was spudded at 10:00 am Central European Time on the 13th of November 2023 using the RED Drilling
& Services GmbH (RED) E-202 rig. The Anshof-2 well is located in the ADX-AT-II license in Upper Austria.
The preliminary petrophysical analysis of the Eocene sandstone reservoirs’ Logging results confirms 12 metres
of net vertical thickness of high quality reservoir with a porosity of approximately 20%. The calculated oil
saturation across the interval is approximately 34%. Oil shows (fluorescence and good chloroform test reaction)
at the top of the Eocene section indicate that higher oil saturations can be expected slightly further up-dip from
the Anshof-2 bottom hole location. Updated structure maps based on the top Eocene being encountered
shallower than prognosis also support this interpretation. Refer to figure 2.
Implications of Anshof-2 Well Results
The preliminary interpretation of the Anshof-2 well results based on an initial petrophysical analysis indicates oil
saturation values at this location are considered too low to complete the well as a producer however oil shows
at the top of the Eocene section indicate that higher oil saturations can be expected slightly further up-dip from
the Anshof-2 bottom hole location. The well has therefore been suspended to be side tracked as a future oil
producer up-dip from the current well location.
The Anshof-2 well was drilled as an appraisal well targeting a down dip location from the Anshof-3 discovery
well in order to prove an oil water contact (or oil down to) based on pre-drill mapping more than 100 metres
deeper than the “oil down to” (ODT) encountered in the Anshof-3 well.
The implications of the drilling and logging results at Anshof-2 for the ongoing development of the Anshof field
are as follows:
1. The reservoir quality (20% porosity) and net reservoir thickness (12 metres net vertical thickness) is
outstanding and is in line with ADX’ pre drill upside case (P10) model. This model also predicts similar
reservoir quality and more net reservoir thickness further up-dip from the Anshof-2 bottom hole location.
The vertical thickness of net reservoir at the Anshof-2 location is approximately 5 times that encountered at
the Anshof-3 discovery well providing very positive implications for productivity of a future up-dip producer.
2. The well came in 40 to 50 metres higher than prognosis, hence the revised mapping of the field results in a
larger area of the Anshof Field being significantly above the ODT proven in the Anshof-3 well. This will result
in a significant increase in reserves at the crest of the structure.
The presence of a much thicker than expected high-quality reservoir section and the fact that Anshof oil field
structure is flatter and larger due to the Eocene sands being encountered 40 to 50 metres higher than prognosis
is expected to compensate for the shallower than expected OWC depth at Anshof-2. As a result, a larger crestal
volume with greater reservoir thickness can be expected requiring fewer production wells due to higher well
productivities and reserves recovery per well.
It should be noted that Eocene oil producers in the basin with similar high quality sand intersections as
encountered in Anshof-2 have produced at rates of approximately 1,000 barrels per day.
2|Page
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
Permit:
ADX AT-II
Well scheme
Success case
Well name: ANSHOF 2
UWI: ANS-002
Directional waypoints:
Spud-in point :
E 67587.81
N E; N; TVDSS [m]
5319705.08
Elevation
Target
1: 68351.7; 5319577.8; -1661.8
(MSL): 406.6 m
Target 2: 68600; 5319515; -1711.2
RT above GL: 6,23 m
Target shape:
Polygon
Wellpath: high angle slanted
Scheme not scaled. All depth on this page count from Ground Level.
Depth MD
[m]
Stratigraphy and Mud system
0
100
Quarternery
Flysch
Top depth
[mMD]
0
20
200
300
400
500
Imbricated
Puchkirchen Fm.
400
600
Wellscheme
Casing and Cementation
Directional
Mud and drilling problems
20" Conductor 4 m
13 3/8" 54.5# K55 BTC
130 m
Gel 1.20
K2CO3 Polymer mud
1.25 kg/l
Formation
Shallow
gas 150200 m
Fault
zone
350..390
m
12 1/4" Hole
Class G 1.9 kg/l
KOP @ 450 m
Az. 97.29°
DLS 3°/30 m
EOB @ 650 m
9 5/8" 40# L80-1 BTC
730 m
700
Incl. 20.02°
800
900
IMB PK Gas Sands
874
Class G 1.7 kg/l Lead
1000
1100
1200
K2CO3 Polymer mud 1.30 kg/l
1300
1400
1500
1600
1700
1800
1900
2000
2100 Zupfing Fm.
2073
2200 Eggerding Fm.
2153
2246
2278
2318
Dynow marl
2300 Schoeneck Fm.
Upper Eocene
8 1/2" Hole
KOP 2 @ 1871 m
Az. 104.2°
DLS max. 4°/30m
Class G 1.9 kg/l Tail
EOB 2 @ 2315 m
2400
Incl. 79.10°
2500
2600
Upper Cretaceous
2700 TD (TVD 2132 m)
2598
2650
7", 26 lbs/ft, L80, BTC-TXP
TD 2650 m
EOT @ 2650 m
TVD 2132 m
2800
Figure 1: Anshof-2 pre-drill well (ANS-2) well plan
3|Page
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
Figure 2: Anshof Western Lobe Map schematic showing the area of high quality thick (+10 m) net reservoir areas
in yellow, superimposed by structural contours and the expected ODT up-dip of Anshof-2. A future up-dip
sidetrack for oil production is expected to encounter similar or better reservoir properties than Anshof-2
Future Operations
The RED E-202 drilling rig is expected to be released on the 12th December 2023 following suspension of the
Anshof-2 well for future side track.
The suspension of the well allows the necessary time to determine an optimal well location for a future side
track which is sufficiently up-dip from the Anshof-2 bottom hole location with a reservoir intersection of a similar
or greater thickness of high quality sands. The future drilling of the side track from the bottom of 9 ⅝ inch casing
at Anhof-2 provides significant cost savings for a future development well.
The side track of the well is expected to be undertaken following the drilling of ADX Welchau-1 well.
Well Participation and Operatorship
In accordance with Anshof Discovery Area Partnership agreements, the economic interests in the Anshof-2 well
will be 60% ADX and 40% MND. ADX is the Operator of the Anshof Discovery Area Partnership and the ADXAT-II licence.
XST has elected not to participate in the Anshof-2 well. ADX and MND will fund XST’s share of well costs on
50:50 basis and will in turn obtain the right to 60% and 40% respectively of production from the well unless XST
opts to buy back into the well at a premium of 500% to well costs. XST retains its 20% economic interest in the
remainder of the Anshof Discovery Area Partnership (i.e. Anshof Discovery Area less the Anshof-2 well) with
both ADX and MND’s economic interests remaining at 50% and 30% respectively.
For further details please contact:
Paul Fink
Ian Tchacos
Chief Executive Officer
Executive Chairman
+61 (08) 9381 4266
+61 (08) 9381 4266
paul.fink@adx-energy.com
ian.tchacos@adxenergy.com.au
Authorised for lodgement by Ian Tchacos, Executive Chairman
4|Page
ADX Energy Ltd (ASX:ADX)
ASX RELEASE
Persons compiling information about Hydrocarbons:
Pursuant to the requirements of the ASX Listing Rule 5.31, 5.41 and 5.42 the technical and reserves information
relating to Austria contained in this release has been reviewed by Paul Fink as part of the due diligence process
on behalf of ADX. Mr. Fink is Technical Director of ADX Energy Ltd is a qualified geophysicist with 30 years of
technical, commercial and management experience in exploration for, appraisal and development of oil and gas
resources. Mr. Fink has reviewed the results, procedures and data contained in this release and considers the
resource estimates to be fairly represented. Mr. Fink has consented to the inclusion of this information in the
form and context in which it appears. Mr. Fink is a member of the EAGE (European Association of Geoscientists
& Engineers) and FIDIC (Federation of Consulting Engineers).
Previous Estimates of Reserves and Resources:
ADX confirms that the results of the Anshof -2 well will impact Anshof Field Reserves estimates. ADX will provide
an update in relation to Anshof Field Reserves as soon as practically possible together with all material
assumptions and technical parameters.